House construction photo tour

View from front of

property

View from back of

property

11-4-06  Site is

marked by survey

company

11-9-06  Silt fencing

is rolled out

11-24-06  DIgging

reveals a sewer pipe

under the location of

the house

12-13-06  Digging

resumes, the hole is

getting deeper

12-26-06  Bobcat is

stuck

12-28-06  Footers are

poured

12-29-06  Concrete is

poured into forms to

make the basement

walls

12-30-07  Forms are

removed to reveal the

walls

Site preparation before the house arrives

Page 1 Page 2 Page 3 Page 4 Page 5

Before the house is delivered, the site is

marked and the basement foundation is

prepared.